Advertisement

In ‘aggressive move,’ federal agency overrules New York on pipeline permit

Legal experts predict New York environmental regulators will appeal decision.

Protesters urge the Federal Energy Regulatory Commission to reject a natural gas pipeline proposed by Kinder Morgan in the U.S. Northeast. CREDIT: AP Photo/Charles Krupa
Protesters urge the Federal Energy Regulatory Commission to reject a natural gas pipeline proposed by Kinder Morgan in the U.S. Northeast. CREDIT: AP Photo/Charles Krupa

Federal energy regulators undercut a New York environmental agency Friday, allowing a pipeline company to go forward with a project the state had previously blocked.

The Federal Energy Regulatory Commission (FERC) granted a natural gas pipeline company permission to move forward with its project, even though the New York State Department of Environmental Conservation refused to grant the company a water quality permit required under the Clean Water Act. Under section 401 of the Clean Water Act, states must certify that a pipeline will not violate clean water standards before construction on that pipeline can begin.

FERC ruled the state failed to meet a statutory one-year deadline to act on the permit request and therefore waived its authority to issue a decision on the application. Pipeline opponents criticized the federal commission’s ruling to overturn the state environmental agency’s decision.

“FERC’s reversal of Governor Cuomo’s decision is an insult to New Yorkers and our right to protect our communities and our water,” Roger Downs, director of the Atlantic chapter of the Sierra Club, said in a statement. “States unquestionably have the authority to rule whether a dirty, dangerous fracked gas pipeline violates clean water laws, and nowhere is FERC granted the right to override that authority.”

Advertisement

The New York State DEC said in a statement that it is reviewing FERC’s decision and “will consider all legal options to protect public health and the environment.”

Millennium Pipeline’s proposed Valley Lateral Project, if built, will consist of almost eight miles of pipeline that will feed huge amounts of natural gas to a 680-megawatt power plant in Orange County, New York, under construction by Competitive Power Ventures.

In a similar case, Constitution Pipeline, whose primary owner and developer is Williams Partners LP, sued in May to overturn a water quality permit denial from the New York DEC. Last month, U.S. Court of Appeals for the 2nd Circuit sided with the state, saying it acted within its authority to deny the permits.

But after FERC’s decision in the Millennium Pipeline case, other industry officials are growing optimistic about getting their water permit denials overturned. Williams spokesman Chris Stockton said Constitution Pipeline is now planning to seek a similar Clean Water Act section 401 waiver determination directly from FERC.

Advertisement

National Fuel Gas Supply, another owner of natural gas pipelines in New York, sent a letter to FERC last week asking the agency to overturn the state DEC’s denial of a water certificate for its Northern Access project, which runs from Pennsylvania to New York.

Legal experts are skeptical whether FERC would have made a similar decision on a water certification waiver request during President Barack Obama’s presidency when Democrats chaired the commission. “Historically, FERC has not waded into the fray on the 401 certification fight,” Moneen Nasmith, an attorney with Earthjustice who is representing the Sierra Club on other pipeline fights in New York, told ThinkProgress. “For them to come in and do what they did here is an aggressive move.”

In Friday’s order, FERC wrote: “If a state agency concludes that a certification application does not meet [Clean Water Act] requirements, it can deny the application. New York DEC declined to take that step or to otherwise timely act on Millennium’s application.”

FERC’s ruling was unanimous. President Donald Trump’s two Republican appointees to the commission — Chairman Neil Chatterjee and Commissioner Robert Powelson — joined Cheryl LaFleur, a Democratic commissioner, to vote to overturn the state agency’s ruling.

Advertisement

On August 30, the New York DEC denied Millennium Pipeline’s request for a water permit to build its Valley Lateral Project. In its rejection, the state agency cited a recent court decision in which FERC’s environmental review of a pipeline project in the southeastern United States was found to be inadequate and deficient.

According to the DEC, FERC “failed to consider of quantify the indirect effects of downstream [greenhouse gas] emissions in its environmental review of the project that will result from burning the natural gas that the project will transport to CPV Valley Energy Center.”

For FERC, though, its decision in the Millennium Pipeline case came down to the timing of the state agency’s rejection of the company’s application. The DEC argued that it had one year from the time it deemed the pipeline company’s application complete to issue a decision in the case. The state agency designated the application complete on August 31, 2016, after it had received additional information from the pipeline company.

However, FERC sided with Millennium Pipeline that the clock began running on November 23, 2015, when the DEC first received the company’s application, and that the state agency had until November 23, 2016, not August 31, 2017, to issue a decision on the water quality certification application.

The Clean Water Act specifies that if a state agency “fails or refuses to act on a request for certification within a reasonable period of time (which shall not exceed one year) after receipt of such request, the certification requirements of [section 401] shall be waived with respect so such federal application,” FERC said in its decision.

To support its decision, FERC highlighted a pair of prior decisions in which it concluded that the clock started running once a state agency received a water quality permit application, not when the state regulatory agency concluded the application was complete. The agency cited a ruling it made in 2004 in which it overrod the Washington Department of Ecology’s denial of a natural gas pipeline company’s certification request; the state agency issued its decision “more than two years after receipt” of the pipeline’s application, FERC said.

In a liquefied natural gas import terminal case in Baltimore, FERC ruled that the Maryland Department of the Environment waived its right to rule on the company’s application “by failing to act on the request within one year of receipt of the company’s application.”

Under FERC’s decision, though, a company can simply submit a “super-thin application,” saying, ‘Hey, we want a permit,” Nasmith said. “There’s nothing to stop that from happening now, except that I have no doubt that FERC’s decision will be challenged,” she predicted.

The courts have held that such a type of application cannot be what starts the clock running for regulators who are considering whether to grant a water quality permit, Nasmith said.